Morris-Garner and another (Appellants) v One Step (Support) Ltd (Respondent) [2018] UKSC 20
In Morris-Garner the Supreme Court had the opportunity to consider damages awards for breach of contract based on the price that would have been hypothetically negotiated for releasing the restrictive term. It follows that from handing down of the judgment on 18 April 2018, Morris-Garner is now the leading case on the matter and should be a point of reference for practitioners and employers alike.
Background and Wrotham Park
The remedy for breach of contract is often given little more explanation than the often-repeated phrase: “the measure of damages for breach of contract is to put the innocent party in the position that they would have been in had the contract been performed”. Damages are usually awarded in circumstances where a party can be considered to have suffered some financial loss through breach or non-performance of a contractual term. As such, they are usually considered compensatory. Nonetheless, in some cases, including those where enforcement is sought for breaches of restrictive covenants contained in employment contracts, injunctive proceedings in the High Court are another source of recourse.
There are, however, other scenarios where there is no clear economic loss suffered and an injunctive remedy is considered inappropriate. Wrotham Park Estate Co Ltd v Parkside Homes Ltd [1974] was one such case. In Wrotham Park, a plot of land was sold subject to restrictive covenants on the development of a portion of that land. Ultimately, that land was transferred to a property developer who was not aware of the said restrictions. The developer proceeded to develop the land in breach of that restriction.
Despite being aware of plans to develop the land and a grant of planning permission, the party holding the right to enforce that restrictive covenant only made their objection known when they applied for an interim injunction against the developers. This was after the development had begun. Albeit the injunction was sought at an early stage of the development, Brightman J decided that although the claimant would ordinarily be entitled to an injunction it should be rejected as a matter of discretion. The state of law at the time suggested that no or nominal damages should be awarded as the claimant had suffered no financial damage from the breach of contract. Nevertheless, the claimant was awarded a sum equal to that which the Court considered they would have received on a negotiated release of the restrictive covenant; 5% of the developer’s anticipated profit. The award of damages on the basis of a hypothetical negotiation has until this point tended to be referred to as “Wrotham Park” damages. In Morris-Garner, the Supreme Court said that they prefer to call these “negotiating damages” and therefore we adopt this terminology for the purposes of this article.
The facts of Morris-Garner
Morris-Garner involved a joint venture between two defendants and the claimant. The joint venture provided rented accommodation and support services to enable vulnerable individuals referred by local authorities to live as independently as possible. In 2006, the first defendant transferred her 50% shareholding to the claimant in return for £3.15 million. The first defendant was subjected to confidentiality, non-solicitation and non-competition covenants running for three years. Within the restricted period and in breach of those restrictive covenants the first and second defendant founded and operated a business in competition with that of the claimant. In the words of Lord Reed who delivered the leading judgment on behalf of the Supreme Court in this case:
“[the claimant] sought an account of profits, or alternatively what were described as restitutionary damages, in such sum as it might reasonably have demanded as a quid pro quo for releasing the defendants from those covenants, or, in a further alternative, what were described as compensatory damages for the loss it had suffered by reason of the defendants’ breach of those covenants.”
Emphasis added.
The first instance judge applied Wrotham Park by saying that the claimant could elect to either receive negotiating damages calculated as the fee the defendants would have had to pay to be released from their obligation or alternatively compensatory damages in the form of lost profits or possibly goodwill. At the Court of Appeal, this decision was upheld. That Court considered the test for whether negotiating damages could be awarded was whether an award of damages on that basis was a just response in the particular case which was a matter for the judge to decide on a broad brush basis. The Supreme Court ruled that both the first instance judge and the Court of Appeal had taken an approach that could not be considered to be correct. The salient areas of the judgment in Morris-Garner are set out below.
A theoretical objection?
At paragraph 91 Lord Reed dealt with what some had argued was a bar to the award of damages on a negotiated damages basis, namely that “[t]he use of an imaginary negotiation can give the impression that negotiation damages are fundamentally incompatible with the compensatory purpose of an award of contractual damages”. He did so by stressing that the relevant contractual right should be conceptualised as an asset and an economic value being given to the fact that a party had been deprived of it.
Understanding contractual rights as assets
He also accepted at paragraph 95(9) that the normal inference “[w]here the claimant’s interest in the performance of a contract is purely economic, and he cannot establish that any economic loss has resulted from its breach” would be that they have suffered no loss and in that event, they could not be awarded more than nominal damages. However, he goes on to explain at paragraph 95(10) that “negotiating damages can be awarded for breach of contract where the loss suffered by the claimant is appropriately measured by reference to the economic value of the right which has been breached, considered as an asset”. The hypothetical negotiating is only a means of reaching a value.
No right to elect how damages are assessed
In rejecting the approach taken by both the judge at the first instance and by the Court of Appeal, Lord Reed at paragraph 96 clarified that no claimant is entitled to elect how their damages are assessed. Part of this confusion may have been caused by a misunderstanding of the previous cases which could be seen as treating Wrotham Park assessments as some entirely separate means of assessing damages. Shutting down this view, Lord Reed emphasised that using an imaginary negotiation is “merely a tool” for assessing the value of a financial loss.
Concluding thoughts
Morris-Garner has been remitted to the lower courts for the Court to consider the financial loss and/or loss of goodwill which the claimant has actually sustained.
Claimants should be encouraged in that the Supreme Court has clearly enunciated that an inability to show clear financial loss is not necessarily the be all and end when seeking a damages award for breach for contract.
By providing authoritative clarification on an area of law with confused reasoning, Morris-Garner has narrowed the scope for seeking negotiating damages. The Supreme Court is clear that the ordinary inference if no clear loss can be proven, is that no or nominal damages should be awarded.
Nonetheless, claimants should fully explore recovering damages on a negotiated damages basis where they cannot easily identify a financial loss but can put an objective economic value to a benefit protected by the contractual term that has been infringed.
Negotiating damages are not understood as a departure from ordinary compensatory damages. They are ordinary damages awarded following the use of a hypothetical negotiation used to assist a judge in calculating the economic value of an asset or a right that is taken or infringed through breach of a contractual term.